Scope:
J.R. Abbott
This project was a unique challenge, as the
market was redesigned
after the entire slab was poured. SRI
was called in after two other
companies, that provided similar
services, had failed. With nearly
300 relocated plumbing and
electrical sleeves, radar was essential for
accuracy in
locating smurf, PVC, j-boxes, and rebar.
|

|
|

This image shows rebar and a conduit on the right in
a wavy line.
|
In addition,
radar eliminated
the unnecessary tearing of insulation under the deck
that would have occurred from
using x-ray. This resulted in providing
additional savings for the
client. In most locations it was imperative
not to cut through any reinforcing bar.
With nearly 300
relocated plumbing and electrical sleeves, radar was essential for
accuracy.
|
|
|

The rebar grid pattern (Red) and an clear core location in the
wall. |
With restrictions and limitations from the
architect and engineer, documentation was essential. SRI was able to
provide them with digital pictures and critical information in the time
of need.
In most
locations it was
imperative not to cut through any reinforcing steel.
|
|
SRI pays great attention to details, accurately
displaying what is in the
slab.
|

This image shows rebar ending and conduit changing direction. |
|
|

|
 |
|
|
Here are some examples of the finished cases.
|
| |
|
|